Withdrawn October 2010.
|
|
location:
|
|
Near Concord Street, Newton
Lower Falls, MA 02462, crossing to behind 27 Washington Street,
Wellesley Lower Falls |
|
goals:
|
|
Convert the
unused railroad bridge crossing over the Charles River, just downstream
of Route 16, and the parcels abutting the bridge in Wellesley and
Newton, for use as pedestrian bridge & park. The site
is near existing
trails on the Wellesley side of the river and could be
connected to future pedestrian trails on the Newton
side. |
|
project
funding:
|
|
| design |
| $12,000
|
|
Massachusetts
Dept.
of Conservation & Recreation funds |
| $12,000
|
|
private
matching funds from Wellesley
Trails Committee & Newton Conservators |
$24,000
|
|
TOTAL
DESIGN FUNDING |
|
| |
| construction |
| $46,784 |
|
CP
funds requested in Newton
(recreation
land) |
|
$ |
|
private matching funds for Wellesley
path & park |
| $ |
|
all
costs not covered by Newton or Wellesley to be covered by Massachusetts
Dept. of Transportation (for bridge itself) and Dept. of Conservation
& Recreation (for approaches) through the Accelerated
Bridge Program |
$850,000
|
|
TOTAL
ESTIMATED CONSTRUCTION COST |
|
|
contacts:
|
|
George
Kirby
Newton Bicycle/Pedestrian Task Force Chair
email:
newtonbikeped@gmail.com
phone:
617 . 463 . 2078
Kevin Hollenbeck, West District Urban Parks Manager
Massachusetts Dept. of Conservation & Recreation (DCR)
email:
kevin.hollenbeck@state.ma.us
phone:
617. 333 . 7404, ext. 105
John McInerney,
Division Engineer, Bridge & Tunnel Construction Massachusetts
Dept. of Transportation (DoT)
email:
john.mcinerney@state.ma.us
phone:
617. 561 . 6159
|
|
|
proposal
review & appropriation:
|
|
5 December 2008
|
|
proposal
|
|
5 December 2008
|
|
attachments to
proposal: photos, maps, application for DCR funds
(long file; may take a while to
open)
|
|
14 January 2009
|
|
presentation
to public hearing (includes photos and maps) |
|
2008-09
|
|
Dept.
of Conservation & Recreation presentations (scroll to
see links for "Newton, "Lower Falls," or "Charles River
Footbridges") |
|
2009
|
|
sponsor
updates: |
|
28
August 2009
|
|
cover
memo & background correspondence |
|
28 August 2009
|
|
deed
& plan conveyed to DCR (then the Metropolitan
District Commission) in 1982 |
|
28 August 2009
|
|
project
timeline |
|
28 August 2009
|
|
preliminary
cost estimates |
|
2010
|
|
sponsor
updates: |
|
8 January 2010
|
|
design
(site plan & elevations),
large-scale: requires 24x36 inch paper to print at full size |
|
1 March 2010
|
|
final funding
request, including budget detail and online
request for proposals (RFP) as evidence of state funding
commitment |
|
22 October 2010
|
|
proposal
withdrawn
|
|
|
project
news:
|
|
December 2009
|
|
Wellesley
- preliminary
site plan |
|
17 February 2010
|
|
Wellesley
- process
& funding commitments to date |