2010 Construction Schedule

Street Process Plan Status Contact
Ardmore Rd. 2010 Water Main Construction Work Water main replacement, and cleaning & lining, new water services to property line Installation begins in summer 2010. Contractor:  Granese
Contact:  Angelo Stellato, Engineering Division
Ashmont Ave. Cold Plane and Bituminous Paving

Cold planning (milling) and bituminous concrete pavement overlay of roadway surface

Road paving scheduled for summer 2010. Matt Woodruff, Engineering Division.  Steve Tocci, Highway Division
Audubon Drive 2010 Water Main Construction Work Water main replacement, new water services to property line Installation underway. Contractor:  Cedrone Trucking. Contact:  Angelo Stellato, Engineering Division
Avon Place 2010 Water Main Construction Work Water main replacement and cleaning & lining, new water services to property line. Water main installation underway. Contractor:  Biszko Contracting. Contact:  Gerry O’Shea, Engineering Division.  Tata & Howard Engineers
Bacon Place Cold Plane and Bituminous Paving Cold planning (milling) and bituminous concrete pavement overlay of roadway surface. Road paving scheduled for summer 2010. Matt Woodruff, Engineering Division.  Steve Tocci, Highway Division
Baker Place Cold Plane and Bituminous Paving Cold planning (milling) and bituminous concrete pavement overlay of roadway surface. Cold-Planing scheduled for week of August 23. Matt Woodruff, Engineering Division.  Steve Tocci, Highway Division
Canterbury Rd. Cold Plane and Bituminous Paving Cold planning (milling) and bituminous concrete pavement overlay of roadway surface. Road paving scheduled for summer 2010. Matt Woodruff, Engineering Division.  Steve Tocci, Highway Division
Charles St. 2010 Sewer Main Construction Work Sewer main replacement. Sewer installation is completed.  Roadway improvements scheduled for summer 2010.  RJV Construction. Contact:  Ted Jerdee, Water-Sewer Division.  Weston & Sampson Engineers
Cloverly Rd. Chip Seal 5/8” chip seal material (asphalt, sand and stone) to roadway surface. Chip sealing scheduled for week of August 23. Matt Woodruff, Engineering Division
Commonwealth Ave Phase 3 Reconstruction, Massachusetts Department of Transportation. Reconstruction Reconstruction of Commonwealth Ave and Carriage Way from Grant Ave to 700 ft west of the Boston City line, including new curbing, sidewalks, paving, catch basin repairs, street lights. Construction will continue Summer with roadway reconstruction. Contractor:  Newport Construction Contact:  Frank Nichols, Engineering Division
Cornell St (Grove to Pine Grove) Cold Plane and Bituminous Paving Cold planning (milling) and bituminous concrete pavement overlay of roadway surface. Cold-Planing scheduled for week of August 23. Matt Woodruff, Engineering Division.  Steve Tocci, Highway Division
Cragmore Rd. Cold Plane and Bituminous Paving Cold planning (milling) and bituminous concrete pavement overlay of roadway surface. Road paving scheduled for summer 2010. Matt Woodruff, Engineering Division.  Steve Tocci, Highway Division
Crescent St. Microsurfacing Microsurfacing Scheduled for August 19 & 20, 2010. Matt Woodruff, Engineering Division.  Steve Tocci, Highway Division
Elm St. 2010 Water Main Construction Work Water main replacement, and cleaning & lining, new water services to property line. Installation begins in summer 2010.

Contractor: Granese
Contact: Angelo Stellato

Fairview Terr. 2010 Water Main Construction Work Water main replacement, and cleaning & lining, new water services to property line. Installation begins in summer 2010.

Contractor:  Granese
Contact:  Angelo Stellato, Engineering Division.

Frances St. 2010 Sewer Main Construction Work Sewer main replacement. Sewer installation is completed.  Roadway improvements scheduled for summer 2010.  RJV Construction. Contact:  Ted Jerdee, Water-Sewer Division.  Weston & Sampson Engineers
Gibbs Rd. Cold Plane and Bituminous Paving Cold planning (milling) and bituminous concrete pavement overlay of roadway surface. Road paving scheduled for summer 2010. Matt Woodruff, Engineering Division  Steve Tocci, Highway Division
Grove St. (I95 - Wash.) Cold Plane and Bituminous Paving Cold planning (milling) and bituminous concrete pavement overlay of roadway surface. Cold-Planing scheduled for week of August 23. Matt Woodruff, Engineering Division.  Steve Tocci, Highway Division
Harvard St.(Farquar Rd to Harvard Cir) 2010 Water Main Construction Work Water main replacement and cleaning & lining, new water services to property line. Water main installation underway. Contractor:  Biszko Contracting. Contact:  Gerry O’Shea, Engineering Division.  Tata & Howard Engineers
Harvard St. Bridge 2010 Bridge Repair Work Mass. Department of Transportation Complete replacement of bridge deck. Underway, completion scheduled for October 2010.  Night work ongoing. Contractor:  Mass DOT. New England Infrastructure. Contact:  Matt Woodruff, Engineering Division
Herrick Rd. - Beacon St Bump-Outs Installation of curbing and bump-outs at Herrick-Beacon St. New gas main installation by National Grid scheduled for summer 2010.  Cold planning and paving scheduled for summer 2011. Matt Woodruff, Engineering Division.  Steve Tocci, Highway Division
Hibbard St. Cold Plane and Bituminous Paving Cold planning (milling) and bituminous concrete pavement overlay of roadway surface. Curb and sidewalk work is underway.  Road paving scheduled for summer 2010. Matt Woodruff, Engineering Division.  Steve Tocci, Highway Division
Hillside Terr. 2010 Water Main Construction Work Water main replacement, and cleaning & lining, new water services to property line. Installation begins in summer 2010. Contractor:  Granese  Contact:  Angelo Stellato, Engineering Division.
Kent Rd. Cold Plane and Bituminous Paving Cold planning (milling) and bituminous concrete pavement overlay of roadway surface. Cold-Planing scheduled for week of August 23. Matt Woodruff, Engineering Division.  Steve Tocci, Highway Division
Kingsbury Rd. Chip Seal 5/8" chip seal material (asphalt, sand and stone) to roadway surface. Chip sealing scheduled for week of August 23. Matt Woodruff, Engineering Division
Lawrence Rd. Chip Seal 5/8" chip seal material (asphalt, sand and stone) to roadway surface. Chip sealing scheduled for week of August 23. Matt Woodruff, Engineering Division
Lewis Terr. 2010 Water Main Construction Work Water main replacement and cleaning & lining, new water services to property line. Water main installation underway Contractor:  Biszko Contracting. Contact:  Gerry O’Shea, Engineering Division.  Tata & Howard Engineers
Littlefield Rd. 2010 Water Main Construction Work Water main replacement, new water services to property line. Installation underway Contractor:  Cedrone Trucking. Contact:  Angelo Stellato, Engineering Division.
Longwood Rd. 2010 Water Main Construction Work Water main replacement, new water services to property line. Installation underway Contractor:  Cedrone Trucking. Contact:  Angelo Stellato, Engineering Division.
Margaret Rd. 2010 Sewer Main Construction Work Sewer main replacement. Sewer installation is completed.  Roadway improvements scheduled for summer 2010.  RJV Construction. Contact:  Ted Jerdee, Water-Sewer Division.  Weston & Sampson Engineers
Meredith Rd. Cold Plane and Bituminous Paving Cold planning (milling) and bituminous concrete pavement overlay of roadway surface. Road paving scheduled for summer 2010 Matt Woodruff, Engineering Division.  Steve Tocci, Highway Division
Moffat Rd. Cold Plane and Bituminous Paving Cold planning (milling) and bituminous concrete pavement overlay of roadway surface. Cold-Planing scheduled for week of August 23. Matt Woodruff, Engineering Division.  Steve Tocci, Highway Division
Myrtle St. 2010 Water Main Construction Work Water main replacement, and cleaning & lining, new water services to property line. Installation begins in summer 2010.

Contractor: Granese
Contact:  Angelo Stellato, Engineering Division.

Nahanton Park 2010 Accessible Access Ramps Construct accessible access ramps at the parks. Construction upcoming in September Contractor:  P. Mastroianni Construction. Contact: Matt Woodruff, Engineering Division
Neal St. Cold Plane and Bituminous Paving Cold planning (milling) and bituminous concrete pavement overlay of roadway surface. Cold-Planing scheduled for week of August 23. Matt Woodruff, Engineering Division.  Steve Tocci, Highway Division
Newtonville Ave. (Harvard St to Oakland St) 2010 Water Main Construction Work Water main replacement and cleaning & lining, new water services to property line. Water main installation underway Contractor:  Biszko Contracting. Contact:  Gerry O'Shea, Engineering Division.  Tata & Howard Engineers

Nonantum Rd.

Mass. DOT

Reconstruction Curbing, sidewalk cold-paving, paving
Underway

Contact:
Frank Nichols
Engineering Division

Normandy St. Microsurfacing Microsurfacing Scheduled for August 19 & 20. Matt Woodruff, Engineering Division.
Old England Rd. Chip Seal 5/8" chip seal material (asphalt, sand and stone) to roadway surface. Chip sealing scheduled for week of August 23. Matt Woodruff, Engineering Division
Old Orchard Rd. Chip Seal 5/8" chip seal material (asphalt, sand and stone) to roadway surface. Chip sealing scheduled for week of August 23. Matt Woodruff, Engineering Division
Pearl Street Parking Lot Reconstruction Full depth reconstruction of Pearl Street. Parking Lot, including new curbing, bituminous concrete paving, and parking pay station. Construction will start in summer 2010. Contractor:  Upcoming Contact:  Matt Woodruff, Engineering Division
Pelham Rd. 2010 Water Main Construction Work Water main replacement, and cleaning & lining, new water services to property line. Installation begins in summer 2010.

Contractor:  Granese
Contact:  Angelo Stellato, Engineering Division.

Pellegrini Park Extraneous improvements Accessible access improvents. Scheduled for summer 2010.

Contractor:
Green Acres
Contact:
Mike Kessman
Engineering Division

Perkins St. 2010 Water Main Construction Work Water main replacement, and cleaning & lining, new water services to property line. Installation begins in summer 2010. Contractor:  Granese
Contact:  Angelo Stellato, Engineering Division.
Pine Grove Ave. 2010 Water Main Construction Work Water main replacement, new water services to property line. Installation underway Contractor:  Cedrone Trucking. Contact:  Angelo Stellato, Engineering Division.
Pine Ridge Rd. Cold Plane and Bituminous Paving Cold planning (milling) and bituminous concrete pavement overlay of roadway surface. Road paving scheduled for summer 2010. Matt Woodruff, Engineering Division.  Steve Tocci, Highway Division
Prospect St.(Washington - Temple) 2010 Water Main Construction Work Water main replacement, and cleaning & lining, new water services to property line. Installation begins in summer 2010. Contractor:  Granese  Contact:  Angelo Stellato, Engineering Division.
Putnam St. (Hunter to Temple) 2010 Water Main Construction Work Water main replacement, and cleaning & lining, new water services to property line. Installation begins in summer 2010. Contractor:  Granese  Contact:  Angelo Stellato, Engineering Division.
Ransom Rd. Cold Plane and Bituminous Paving Cold planning (milling) and bituminous concrete pavement overlay of roadway surface. Road paving scheduled for summer 2010. Matt Woodruff, Engineering Division.  Steve Tocci, Highway Division
Richfield Rd. Cold Plane and Bituminous Paving Cold planning (milling) and bituminous concrete pavement overlay of roadway surface. Road paving scheduled for summer 2010. Matt Woodruff, Engineering Division.  Steve Tocci, Highway Division
Ridgeway Terr. Cold Plane and Bituminous Paving Cold planning (milling) and bituminous concrete pavement overlay of roadway surface. Road paving scheduled for summer 2010. Matt Woodruff, Engineering Division.  Steve Tocci, Highway Division
Robinhood Rd. Microsurfacing Microsurfacing Schudeled for August 19 & 20. Matt Woodruff, Engineering Division. 
Rolling Lane (Brookline - High Rock) 2010 Water Main Construction Work Water main replacement, new water services to property line. Installation underway Contractor:  Cedrone Trucking. Contact:  Angelo Stellato, Engineering Division.
Sharon Ave.


Microsurfacing

 


Microsurfacing.
Scheduled for August 19 & 20. Matt Woodruff, Engineering Division.
Shaw St. 2010 Water Main Construction Work Water main replacement, and cleaning & lining, new water services to property line. Installation begins in summer 2010. Contractor: Granese  Contact:  Angelo Stellato, Engineering Division.
Sterns Park Playground 2010 Accessible Access Ramps Construct playground improvements to the park. Construction underway Contractor: 
CER-Trom construction
Contact: Mike Kessman, Engineering Division
Summer St. 2010 Water Main Construction Work Water main replacement, and cleaning & lining, new water services to property line. Installation begins in summer 2010. Contractor:  Granese
Contact:  Angelo Stellato, Engineering Division
Thornton St. 2010 Water Main Construction Work Water main replacement and cleaning & lining, new water services to property line. Water main installation underway. Contractor:  Biszko Contracting. Contact:  Gerry O’Shea, Engineering Division.  Tata & Howard Engineers
Vine St. (Brookline - Wayne) Cold Plane and Bituminous Paving Cold planning (milling) and bituminous concrete pavement overlay of roadway surface. Road paving scheduled for summer 2010. Matt Woodruff, Engineering Division.  Steve Tocci, Highway Division
Waldorf Rd. Cold Plane and Bituminous Paving Cold planning (milling) and bituminous concrete pavement overlay of roadway surface. Road paving scheduled for summer 2010. Matt Woodruff, Engineering Division.  Steve Tocci, Highway Division
Washington St. (Court - Jackson, S.) Cold Plane and Bituminous Paving Cold planning (milling) and bituminous concrete pavement overlay of roadway surface. Road paving scheduled for summer 2010. Matt Woodruff, Engineering Division.  Steve Tocci, Highway Division
Washington St. (Lowell Ave) Cold Plane and Bituminous Paving Cold planning (milling) and bituminous concrete pavement overlay of roadway surface. Road paving scheduled for summer 2010. Matt Woodruff, Engineering Division.  Steve Tocci, Highway Division
Weir St. Microsurfacing Mircrosurfacing Scheduled for August 19 & 20. Matt Woodruff, Engineering Division. 
Westview Terr. 2010 Water Main Construction Work Water main replacement, and cleaning & lining, new water services to property line. Installation begins in summer 2010. Contractor:  Granese
Contact:  Angelo Stellato, Engineering Division.
Willard St. 2010 Water Main Construction Work Water main replacement, and cleaning & lining, new water services to property line. Installation begins in summer 2010. Contractor:  Granese
Contact:  Angelo Stellato, Engineering Division.
Winthrop St. 2010 Water Main Construction Work Water main replacement, and cleaning & lining, new water services to property line. Installation begins in summer 2010. Contractor:  Granese
Contact:  Angelo Stellato, Engineering Division.
Wiltshire Ct. 2010 Water Main Construction Work Water main replacement, and cleaning & lining, new water services to property line. Installation begins in summer 2010. Contractor:  Granese
Contact:  Angelo Stellato, Engineering Division.
Windsor Rd. Cold Plane and Bituminous Paving Cold planning (milling) and bituminous concrete pavement overlay of roadway surface. Cold-Planing scheduled for week of August 19& 20. Matt Woodruff, Engineering Division.  Steve Tocci, Highway Division
Woodman Rd. Chip Seal 5/8 chip seal material (asphalt, sand and stone) to roadway surface. Chip sealing scheduled for week of August 23. Matt Woodruff, Engineering Division