Harvard Street/Newtonville Avenue
Water Main Replacement Project
The water main on Harvard St is being replaced, along with the water
services. Roadway paving will take place in 2011.
The contractor needs another 3 to 4 weeks to finish water work on Harvard
from Newtonville Ave to Cabot St. He needs another 3 to 4 weeks to finish
water work from Cabot St to the end of Harvard St.
Newtonville Ave is nearly completed, and will be finished by Friday.
The Harvard St bridge is being constructed by Mass DOT. They anticipate
finishing by late September or early October.